Letter to H J H King & Co, engineers, Nailsworth, Thu 21 Dec 1922

< >

Thu 21 Dec 1922
To H J H King & Co, engineers
Nailsworth

Summary

Preliminary inspection shows that when swung both ends of the bridge will be well above the road level at both ends. What steps are you taking to remedy this? Re ballasting, the contract states that our Company is only to supply the planks.

< >