Wed 30 Jul 1856
Committee proceeded by railway to Thames Head.
New engine examined.
Gradual subsidence in the pump. Mr Taunton to propose action.
Examination of Tunnel. Difference in depth by pitching at bottom of Tunnel having lifted. Mr Taunton to prepare report of expense of removing obstacle.
Mr Knight’s drawback continued.
Survey of canal from Lechlade to Stroud. (No details)